Skip to content
Merged
Show file tree
Hide file tree
Changes from all commits
Commits
File filter

Filter by extension

Filter by extension

Conversations
Failed to load comments.
Loading
Jump to
Jump to file
Failed to load files.
Loading
Diff view
Diff view
56 changes: 42 additions & 14 deletions docs/project/charter.md
Original file line number Diff line number Diff line change
Expand Up @@ -34,20 +34,44 @@ Karim's 500-member server is the first one, not the product.

## Success criteria

**1. Twenty members still copying at day 30, on 2026-12-31.** This is the decider's own
stopping rule, and it tests the one claim two independent challenges failed to refute: that a
member copies because someone they know vouched, not because a ranking said so. It is observed
from the members' public addresses on the venue.

**Recorded honestly, because it is written in the discovery and must not be lost here:** this
criterion decides **interest, not viability**. Twenty copiers produce between 41 € and 671 € a
month at the measured turnover. The decider chose it deliberately over a revenue condition:
the first proof sought is use.

**2. More than 500 € of commission in a calendar month, before 2027-03-21.** *(framer, to
confirm — it is the restatement proposed for PDR-0001, whose current criterion is unreachable
at the measured turnover.)* This is the one that tests viability. It needs roughly 98,000 € of
member capital under copy. Observed from the builder fee credited on-chain.
**Revised on 2026-09-22 by [PDR-0003](../pdr/0003-prove-the-machine-on-a-few-before-opening-the-tap.md)**,
which replaced a count with evidence of quality and moved the commission criterion behind a
gate. This section states what that decision says; where the two disagree, the PDR wins. It is
written out here because the PDR was merged with this section left as it was, and the open
questions below claimed a revision the criteria above did not carry.

**Phase 1 — a closed pilot, 5 to 8 members and 2 to 3 traders, before 2026-12-31.** Five
criteria, every one observed rather than asserted:

1. **Zero unchosen divergence** between the member's position and the vouched trader's: the copy
is faithful, or it refuses and says so. It is the product's whole promise — if it drifts
silently, nothing else counts.
2. **Zero key incident.** The agent key can place orders and nothing else, throughout. A decider
no-go, verified rather than asserted.
3. **Every member revokes at least once, deliberately, and it works.** An exit that has never
been used is not an exit.
4. **At least 60% of members choose to continue past day 14.** The only desire signal a pilot can
honestly produce.
5. **`screening`'s predictions confronted with reality** — fees actually incurred, share of
orders refused, slippage between the trader's fill and the member's. The most valuable of the
five, and only a small pilot produces it: it makes falsifiable everything that module has been
asserting.

**Why the count went.** The earlier criterion — twenty members still copying at day 30 — was not
excused, it was arithmetically out of reach at pilot size: this project's own binomial model
showed five invitations returning *refuted* **47% of the time while the product was exactly as
good as forecast**. A criterion that fires on noise is worse than none, because it will be
believed. PDR-0003 carries the model.

**Phase 2 — the acquisition funnel, gated on two conditions**, not one: the written legal opinion
received *and acted on*, **and** every phase-1 criterion met. The funnel may be built meanwhile —
a landing page and a waiting list cost nothing and expose nothing. The tap does not open.

**The commission criterion lives there now**: more than 500 € in a calendar month, testing
viability, needing roughly 98,000 € of member capital under copy, observed from the builder fee
credited on-chain. **Its date is owed by the decider** — PDR-0003 moved it to phase 2 "with a
later date" and named none, so the old *before 2027-03-21* is not restated here as though it had
survived. See the open questions.

## Constraints

Expand Down Expand Up @@ -173,6 +197,10 @@ The pilot size is a **launch** parameter. It gates no deliverable and no module.
**Previously blocking, answered when this charter was accepted:** the **criticality**
(`critical`) and **success criterion 2** (the 500 € restatement proposed for PDR-0001).

**Owed by the decider, since 2026-09-22:** the **date** on the phase-2 commission criterion.
PDR-0003 moved it there "with a later date" and named none. Until it has one, the project has a
viability criterion with no deadline, which is a criterion that cannot fail.

**Not blocking:**

- The written legal opinion, requested and pending.
Expand Down
111 changes: 108 additions & 3 deletions docs/project/cycles/02-make-the-answer-trustworthy.md
Original file line number Diff line number Diff line change
@@ -1,6 +1,6 @@
---
goal: "Find out whether vouching moves anyone, and make the screening answer one an administrator can act on"
status: accepted
status: closed
appetite_weeks: 3
start: 2026-09-21
end: 2026-10-12
Expand All @@ -26,14 +26,16 @@ deliverables:
- id: D3
title: "Three verdicts instead of two, so the headline cannot say yes to a trader the answer is warning about"
module: screening
state: ready
state: accepted
acceptance:
- "Given a trader who clears the floor and trips no reservation, when the command runs, then the verdict is COPYABLE and the exit code is 0"
- "Given a trader who clears the floor with a fee burden above the alert, when the command runs, then the verdict is COPYABLE WITH RESERVATIONS, the fee reservation is named on the first line, and the exit code is 1"
- "Given a trader who clears the floor with more than half their fills posted, when the command runs, then the verdict is COPYABLE WITH RESERVATIONS and the reproducibility reservation is named"
- "Given a trader who clears the floor whose volume landed on a third or less of the days, when the command runs, then the verdict is COPYABLE WITH RESERVATIONS and the concentration reservation is named"
- "Given a trader who does not clear the floor, when the command runs, then the verdict is NOT COPYABLE and the exit code is 2, whatever the reservations say"
- "Given the venue cannot be read, when the command runs, then the verdict is NO VERDICT and the exit code is 3"
outcome: shipped
ended_on: 2026-09-23
---

# Cycle 02 — Make the answer trustworthy
Expand Down Expand Up @@ -151,4 +153,107 @@ copy a trader, and that this was a decision rather than an oversight.

## Closure

<Written at the end of the cycle.>
**Closed on 2026-09-23, on day 3 of a 21-day appetite, with two deliverables accepted and one
never started.**

`shipped`, not `completed`: `completed` would claim every deliverable was accepted, and D1 was
not. Nor is this the circuit breaker — the end date was 19 days away. The decider closed early
because everything this cycle could do with engineering was done, and the one thing left is not
engineering.

## What was delivered

**D2 — the window read. Accepted (#20).** The venue answers ascending and caps a page, so paging
forward from thirty days back spent the budget on the oldest fills and died before reaching the
present: live, it returned a window ending eleven days before the question. The read now walks
backwards from now, sized from one cheap probe. The window ends at the moment of the run —
measured at 0 ms — and a sparse trader costs zero heavy reads where a dense one costs 20 of a
20 budget. This is the S8 failure that stopped cycle 01, closed.

**D3 — three verdicts. Accepted (#26).** `COPYABLE` / `COPYABLE WITH RESERVATIONS (…)` /
`NOT COPYABLE (…)` / no verdict, exit codes 0/1/2/3 by severity, four reservations named in the
headline, and a ceiling that refuses to answer at all past 30× rather than printing an inference
as a fact. Its six acceptance criteria were verified at the head commit by a delegated session
that had refused the branch five times.

**D1 — five private invitations. Deferred, for the second cycle running.** Nobody has been asked.
Ten traders and twenty members are *reported* as wanting to test the bot; that is private,
declarative, and nobody has acted. The cost of this deliverable is five messages and fourteen
days of waiting, and it has now not been paid twice.

**Not in the deliverables, and worth more than one of them:** ADR-0002 (a delegated session may
verify and signs as itself), ADR-0003 (the verification budget follows criticality; no unasked
change inside a fix), PDR-0002 accepted with four amendments, PDR-0003 (a closed pilot before any
funnel), and `handover.md`, which is why a session with no memory could pick this up at all.

## Which success criteria moved

**Neither. Not one.**

The charter's criteria, as PDR-0003 revised them, are five phase-1 conditions about a closed
pilot: faithful copying, zero key incident, revocation that works, 60% continuing past day 14, and
`screening`'s predictions confronted with reality. **Every one of them needs the copying module,
which does not exist.** The fifth is the only one this cycle touched, and only by making it
possible: the module now states a fee burden, a refused share and a reproducible share precisely
enough to be *wrong*. Nothing has confronted them with a member's actual fills, because no member
has any.

**The sentence this closure owes, promised in advance when the cycle was framed:** the project
built a tool for choosing traders with no evidence that any member wants to copy one, and that was
a decision rather than an oversight. It was offered one week on D1 alone, two on D1 and the window
fix, or three on everything; it chose three on everything, and was told at the time that the third
option had the same shape as cycle 01. It did not repeat cycle 01 — both engineering deliverables
landed, in three days. It repeated the other half: **the deliverable that was somebody else's
calendar did not move, and 19 days of appetite are unspent because the appetite was sized for work
cycle 01 had already done.**

## What this cycle cost, measured

D3 alone took **six adversarial rounds and six confirmation runs**. Eleven real defects in the
rounds; **five refusals** in the confirmations, every one correct. The distribution is the finding:

| Origin | Count |
|---|---|
| Defects in the original implementation | 4 |
| Defects the author introduced in later rounds, in changes nobody asked for | 3 |
| Refusals over a **sentence** in the decision record rather than over code | 3 |

The first blocker survived six rounds for a reason that should be read twice: **all 20 `main(...)`
calls in the suite passed `client=`**, so the one line an administrator's own invocation runs was
exercised by no test. Seventy-five green tests were green on a path nobody takes.

What ended the sequence was not another fix. The guarantees in PDR-0002 gained one sentence above
all three — *they speak about what the command chooses to write* — which closed a family instead of
an instance, and the verifier then bounded it: two write sites, enumerated statically and
confirmed by instrumenting 18 paths. **A per-instance clause produces one refusal per round; a
class-level one ends the round.** That is the transferable lesson of this cycle and it belongs in
the next one.

## What was deferred, and why

- **D1**, unchanged and now urgent rather than merely owed. It gates the charter's whole phase 1.
- **Ten follow-ups on `screening`**, listed in #26. The ones that matter: input validation is now
load-bearing for two of PDR-0002's caveats, and the thresholds' calibration — a headline saying
`COPYABLE` over a body warning that 20% of orders cannot be placed — belongs with the PDR's own
success-criterion review.
- **Observability**, carried from cycle 01 for the second time: no retry-rate metric, the 429
deviation unrecorded, and a 60-second budget that is per call where one invocation makes several.
- **The phase-2 date** on the commission criterion, owed by the decider since PDR-0003 moved it
"with a later date" and named none. Recorded in the charter's open questions.
- **`.claude/` project settings and hooks**, untracked and deliberately not gitignored. They are
masked as character devices inside the agent's sandbox, so no agent can read them or commit what
it has not read. A human has to add them.

## Where the next framing starts

**With the copying module, and with the honest reading above rather than with this backlog.**

It is `critical`: it holds a key and moves a member's money. Two things are not negotiable there
and they are tests, not process — the agent key can place orders and nothing else, and revocation
works. Two commitments from `pilot-faq.md` must be framed *with* the module rather than around it:
the notice shown **before** a member acts, and revocation as a first-class path.

And D1 belongs on day one again, for the third time, because the alternative is to build a
`critical` module for a demand nobody has observed. Cycle 01 was told this. Cycle 02 was told this
and chose otherwise, with the reason recorded. If cycle 03 defers it again, that is the project's
answer about what it is really doing, and it should be written down as plainly as this.